TY - JOUR
T1 - Resource-financed infrastructure
T2 - Thoughts on four chinese-financed projects in uganda
AU - Ogwang, Tom
AU - Vanclay, Frank
N1 - Funding Information:
The research design for the research in this paper was a multi-case case-study [78,79]. We examined four cases of resource-financed infrastructure in Uganda: the Kampala– Entebbe Expressway; the Karuma Hydroelectric Dam; the Isimba Hydroelectric Dam; and the section of the East Africa Standard Gauge Railway from Malaba (on the border with Kenya) to Kampala (the capital of Uganda) (see Figure 1). These projects were at different stages of planning and implementation. As at early 2021, three projects had been funded by the China Exim Bank, with the Standard Gauge Railway yet to secure funding. The four projects were selected because, at the time our research commenced, they were the largest RFI projects being developed in Uganda. In our results section (Section 6), for each project, we briefly outline the potential benefits, harms and financing arrangements. In Section 7, we undertake a qualitative meta-analysis to consider whether, across the four cases, the financing arrangements were appropriate and effective from Uganda’s perspective.
Funding Information:
The 183 MW Isimba Hydroelectric Dam project commenced construction in April 2015 and became operational in March 2019. Following the objection regarding the contracting process for the Karuma Dam (Case 2), the China International Water and Electric Corporation (CWE) was directly awarded the contract to build the Isimba project in a Presidential Directive dated 24 July 2013. The project comprised construction of the Isimba Dam and power station, a 132 kv substation, and the 41 km Isimba–Bujagali transmission line. The total cost of these projects was USD $568 million, of which 85% ($482 million) was funded by a PEBC loan from the China Exim Bank, with the balance ($86 million) being provided by the Government of Uganda [105]. Given that China Exim Bank’s PEBC application procedures require a signed commercial contract to be included, a Memorandum of Understanding between the Government of Uganda and CWE was signed on 22 July 2013 to secure funding [105]. The loan was awarded in 2014.
Publisher Copyright:
© 2021 by the authors. Licensee MDPI, Basel, Switzerland.
PY - 2021/3/2
Y1 - 2021/3/2
N2 - Increasingly common methods for financing public infrastructure in developing economies are Resources-for-Infrastructure (R4I) and Resource-Financed Infrastructure (RFI), usually involving Chinese financial institutions and Chinese construction companies. Although there are advantages to the borrowing country from these project financing arrangements, there are also various issues and governance challenges. In Uganda, expectations around future revenue from oil extraction have led to many infrastructure projects being commissioned, mostly funded by RFI arrangements. To consider the appropriateness of these arrangements and to reflect on whether they are likely to contribute to positive development outcomes or be examples of the resource curse, we examined four public infrastructure projects: Kampala–Entebbe Expressway; Karuma Hydroelectric Dam; Isimba Hydroelectric Dam; and the Malaba to Kampala section of the East Africa Standard Gauge Railway. Although R4I/RFI arrangements are viewed positively by some commentators, others (especially local companies) consider they lack transparency, create unsustainable debt, promote China’s interests over the borrowing country, increase unemployment, unfairly compete with local business, deal in corruption, have poor working conditions, and result in substandard construction. Nevertheless, we conclude that Uganda and other developing countries have generally benefited from Chinese-funded infrastructure, and there is more myth trap than debt trap. However, to ensure positive development outcomes, governments and construction companies should ensure compliance with international standards, especially relating to: environmental and social impact assessment; human rights; benefit-sharing arrangements; livelihood restoration; and project-induced displacement and resettlement.
AB - Increasingly common methods for financing public infrastructure in developing economies are Resources-for-Infrastructure (R4I) and Resource-Financed Infrastructure (RFI), usually involving Chinese financial institutions and Chinese construction companies. Although there are advantages to the borrowing country from these project financing arrangements, there are also various issues and governance challenges. In Uganda, expectations around future revenue from oil extraction have led to many infrastructure projects being commissioned, mostly funded by RFI arrangements. To consider the appropriateness of these arrangements and to reflect on whether they are likely to contribute to positive development outcomes or be examples of the resource curse, we examined four public infrastructure projects: Kampala–Entebbe Expressway; Karuma Hydroelectric Dam; Isimba Hydroelectric Dam; and the Malaba to Kampala section of the East Africa Standard Gauge Railway. Although R4I/RFI arrangements are viewed positively by some commentators, others (especially local companies) consider they lack transparency, create unsustainable debt, promote China’s interests over the borrowing country, increase unemployment, unfairly compete with local business, deal in corruption, have poor working conditions, and result in substandard construction. Nevertheless, we conclude that Uganda and other developing countries have generally benefited from Chinese-funded infrastructure, and there is more myth trap than debt trap. However, to ensure positive development outcomes, governments and construction companies should ensure compliance with international standards, especially relating to: environmental and social impact assessment; human rights; benefit-sharing arrangements; livelihood restoration; and project-induced displacement and resettlement.
KW - China Belt and Road Initiative
KW - China Exim Bank
KW - China in Africa
KW - Elite capture
KW - Environmental
KW - Extractive industries and society
KW - International development finance
KW - Megaprojects
KW - Nigerian disease
KW - Resource governance
KW - Social and governance issues
UR - http://www.scopus.com/inward/record.url?scp=85103404866&partnerID=8YFLogxK
U2 - 10.3390/su13063259
DO - 10.3390/su13063259
M3 - Article
AN - SCOPUS:85103404866
SN - 2071-1050
VL - 13
JO - Sustainability (Switzerland)
JF - Sustainability (Switzerland)
IS - 6
M1 - 3259
ER -